Where To Turn home page
 CalendarCalendar   FAQFAQ   SearchSearch   MemberlistMemberlist   UsergroupsUsergroups  ResourcesResources   RegisterRegister 
 ProfileProfile   Log in to check your private messagesLog in to check your private messages   Log inLog in 
Calendar 
Calendar eventCalendar
Tue Apr 25
Wed Apr 26
Thu Apr 27
Fri Apr 28
Sat Apr 29
Sun Apr 30
Mon May 01
LMDC E-update # 77

 
Post new topic   Reply to topic    Where To Turn Forum Index -> Announcements/Events
View previous topic :: View next topic  
Author Message
DMCKEON
Site Admin


Joined: Mar 17, 2005
Posts: 22572
Location: Staten Island

PostPosted: Mon Feb 02, 2009 10:07 am    Post subject: LMDC E-update # 77
From Mon Feb 02, 2009 3:00 am to Thu Feb 05, 2009 2:59 am (included)
Reply with quote

February 2009 Progress Report on the Abatement and Deconstruction of 130 Liberty Street



Below is the February 2009 monthly progress report on the abatement and deconstruction of 130 Liberty Street. This report includes updates on the progress of work in the building and future milestones in the abatement and deconstruction process.



130 Liberty Street Progress and Milestones as of February 1, 2009



Abatement Status



Floors 7 and 6 have been abated and were approved by the New York State Department of Labor (DOL), the Federal Environmental Protection Agency (EPA), and the New York City Department of Environmental Protection (DEP) in mid-January. Overall, all floors down through the 6th have now been abated and cleared by DOL, EPA and DEP.


Abatement continues to proceed in accordance with the Implementation Plan and Emergency Health and Safety Plan (EHASP) for the abatement of 130 Liberty Street, which was approved February 8, 2008.


Abatement on floors 4 and 5 is expected to be complete by February 10, 2009.


Abatement on floors 1 through 3 remains on schedule to be complete by the end of March 2009. Specifically, full abatement has started on floors 2 and 3 and abatement on the first floor will begin shortly.


The building facade has been removed down to the 17th floor, and the facade abatement and removal remains on schedule to be complete by April 23, 2009.


Deconstruction Status



As reported in January, deconstruction will resume once the abatement of floors 1 through 3 is complete, the facade is removed, and a revised Implementation Plan and EHASP incorporating deconstruction activities are approved by the relevant government agencies.


The regulatory agencies provided comments to the drafts of both the Implementation Plan and the EHASP governing the deconstruction. These comments were addressed and the draft plans have been resubmitted to the proper agencies and are currently under further regulatory review. LMDC will post the draft plans on its website in February and will host a meeting for public comment at least two weeks after the posting.


Based on the current progress of work, the expected completion of deconstruction remains fall 2009 as first reported in January.




For further information on the Deconstruction of 130 Liberty please review http://renewnyc.com/plan_des_dev/130liberty/ and

http://www.lowermanhattan.info/construction/project_updates/130_liberty_street__77170.aspx
Back to top
View user's profile Send private message
Display posts from previous:   
Post new topic   Reply to topic    Where To Turn Forum Index -> Announcements/Events All times are GMT - 5 Hours
Page 1 of 1

 
Jump to:  
You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot vote in polls in this forum
You cannot attach files in this forum
You can download files in this forum


Powered by phpBB © 2001, 2005 phpBB Group

 
Credits | Contact Us | Privacy Policy